SCHRADERGROUP Construction Progress – May 2021

As summer quickly approaches, construction work continues to accelerate on SCHRADERGROUP (SG) projects! The team has been hard at work with construction administration for a variety of projects, with some rapidly approaching final completion. A few of our construction projects underway include a new Emergency Operations Center in North Carolina, additions and renovations to the School District of Philadelphia’s Anne Frank Elementary School, the Community College of Philadelphia’s new Career and Advanced Technology Center, the new Upper Merion Area High School, and the new PennDOT District 6.0 Regional Traffic Management Center and Parking Structure, among others. A brief description of a few projects follow.

Chatham County, North Carolina – Emergency Operations Center (EOC)

Chatham_SCHRADERGROUP_May-Construction-Progress
In North Carolina, the grading of the site for the new Emergency Operations Center continues. Fine grading is completed on the east side of the site while work continues on the west side. The temporary entrance to the site has been removed and graded and work with the North Carolina Department of Transportation to connect the main entrance to the roadway has begun. Finally, the Cell Tower Structure was recently installed and the screening topsoil is complete.

School District of Philadelphia – Anne Frank Elementary School

1-Anne-Frank_SCHRADERGROUP_May-Construction-Progress

In Philadelphia, the additions and renovations to Anne Frank Elementary School are quickly progressing. The exterior brick work is now complete and the installation of windows and ceramic tile begins. Inside, the painting is still in progress while the acoustic ceiling tile grid installation begins.

2-Anne-Frank_SCHRADERGROUP_May-Construction-Progress

Community College of Philadelphia – Career and Advanced Technology Center

1-CCP-CATC_SCHRADERGROUP_May-Construction-Progress

In West Philadelphia, the steel framing is complete at the new Career and Advanced Technology Center for the Community College of Philadelphia and the crane has been removed. MEP rough ins above grade have started in addition to the Concrete Masonry Unit walls. This project is scheduled for substantial completion by February 2022.

2-CCP-CATC_SCHRADERGROUP_May-Construction-Progress

Upper Merion Area School District – Upper Merion Area High School

1-Upper-Merion-Area-High-School_SCHRADERGROUP_May-Construction-Progress

In King of Prussia, foundation work continues in the performing arts and gym/pool area of the new high school. In the classroom wing, concrete slabs have been poured. Out front, the curbs and asphalt have been installed in the parking lot. The most exciting update this month is that the site contractor is preparing to connect the site’s existing stream to the renovated stream area, which will be located near an outdoor amphitheater and teaching area to provide the students with science-based learning activities directly related to their campus.

2-Upper-Merion-Area-High-School_SCHRADERGROUP_May-Construction-Progress

Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC) and Parking Structure

1-RTMC_SCHRADERGROUP_May-Construction-Progress

Another SG project in King of Prussia, the new RTMC facility’s foundation is progressing nicely. Heim Construction continues to advance the concrete footings and foundation walls. This week, waterproofing of the concrete footings began as well.

2-RTMC_SCHRADERGROUP_May-Construction-Progress

The new adjacent parking structure is swiftly approaching completion. Installation of metal panel and soffit systems at the Penthouse are underway. The glazing, batten installation, metal louvre, site sign foundation, parking striping, and asphalt paving are all complete. Additionally, electric charging stations have been installed.

3-RTMC_SCHRADERGROUP_May-Construction-Progress

As the weather improves and work continues, it is exciting to watch these projects come to fruition. We would like to thank all of our clients, consultants, contractors, and supporters for your dedication and support!

Learn more about these and other exciting SCHRADERGROUP projects here!

SCHRADERGROUP Construction Progress – April 2021

SCHRADERGROUP’S projects are quickly becoming a reality as construction continued throughout April. The team has been hard at work with construction administration for a variety of projects. A few of our construction projects that are underway include: two projects for the School District of Philadelphia, the Community College of Philadelphia’s new Career and Advanced Technology Center, the new Upper Merion Area High School, and the new PennDOT District 6.0 Regional Traffic Management Center and Parking Structure.

School District of Philadelphia – Anne Frank Elementary School, Renovations

1_SCHRADERGROUP_Anne-Frank-Elementary-School_School-District-of-Philadelphia

Construction continues at Anne Frank Elementary School in northeast Philadelphia. Interior and exterior metal studwork and HVAC ductwork continues while exterior brick work is 80% complete. In the existing building, new VCT flooring has been installed.

2_SCHRADERGROUP_Anne-Frank-Elementary-School_School-District-of-Philadelphia

School District of Philadelphia – Paul L. Dunbar Promise Academy, Masonry Investigation

1_SCHRADERGROUP_Paul-Dunbar-Academy_School-District-of-Philadelphia

Moving into Templetown, masonry restoration work at the Paul L. Dunbar School has finally begun. The historic academy north of center city serves grades k-8 and the façade was in serious need of repair. Old brick parapets were removed and reconstructed with new reinforced and grouted CMU, the exterior brick wythe was reconstructed as well and new flashing and anchors were installed.

This project shows the importance of masonry investigations, as the existing steel angle lintels were severely deteriorated.

2_SCHRADERGROUP_Paul-Dunbar-Academy_School-District-of-Philadelphia

Community College of Philadelphia – Career and Advanced Technology Center, New Facility

1_SCHRADERGROUP_Community-College-of-Philadelphia_Career-and-Advanced-Technology-Center

In West Philadelphia, the new Career and Advanced Technology Center for the Community College of Philadelphia is coming along nicely. The steel frame is being erected from the ground floor level while footings and foundations are ongoing at the first-floor level.

2_SCHRADERGROUP_Community-College-of-Philadelphia_Career-and-Advanced-Technology-Center

Upper Merion Area School District – Upper Merion Area High School, New Facility

1_SCHRADERGROUP_Upper-Merion-Area-School-District-New-High-School

In King of Prussia, the new high school is taking shape. The structural steel and foundation/underground work is ongoing and concrete slabs are underway.

2_SCHRADERGROUP_Upper-Merion-Area-School-District-New-High-School

Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC) and Parking Structure, New Facility

1_SCHRADERGROUP_PennDOT_Regional-Traffic-Management-Center_RTMC

In King of Prussia, the grading for the RTMC building pad is ongoing. Rebar is on site and concrete footings are being poured. The formwork erection for the southwest retaining wall is recently underway.

2_SCHRADERGROUP_PennDOT_Regional-Traffic-Management-Center_Parking-Garage

The parking structure is progressing quickly. The curtain wall framing at the stairs, the stair railing, electrical conduit, and plumbing piping have all been installed and concrete washes are complete. The roof membrane installation has been recently completed as well.

3_SCHRADERGROUP_PennDOT_Regional-Traffic-Management-Center_Parking-Garage

As the weather improves and work continues, it is exciting to watch these projects come to fruition. We would like to thank all of our clients, consultants, contractors, and supporters for your dedication and support!

Learn more about these and other exciting SCHRADERGROUP projects here!