SCHRADERGROUP Construction Progress – Summer 2021
As we move into the middle of summer, many of our construction projects are now really starting to take shape. A few of the construction projects underway include the new Upper Merion Area High School, additions and renovations to Anne Frank Elementary School for the School District of Philadelphia, the new Career and Advanced Technology Center for the Community College of Philadelphia, the masonry restoration of the Paul L. Dunbar School in Philadelphia, the demolition of the existing Springfield High School, and the PennDOT District 6.0 Regional Traffic Management Center, among others.
Upper Merion Area School District – Upper Merion Area High School, New Facility
Construction on the new Upper Merion Area High School continues into the heat of the summer. Infrastructure is being installed and is on pace for a September 2022 completion, just in time for Upper Merion Area School District high school students to start their new school year. Upon completion of and move into the new facility, demolition of the existing facility will begin. Once that demolition is complete, new playing fields will be constructed in its place.
This month, large Glulam Beams continue to be erected in the common areas. In the theater wing, the steel is in place for the stage as the auditorium takes shape.
School District of Philadelphia – Anne Frank Elementary School, Additions and Renovations
Work on the Anne Frank Elementary School continues in Northeast Philadelphia. Metal panels have been installed on 75% of the new construction areas while the glass and glazing installation is 50% complete.
Acoustic ceiling tile and vinyl composite tile installation continues while the walls are being painted. Ceramic tile flooring has started in the toilet rooms as well. A new feature this month are the railings being installed in the new stairways.
Community College of Philadelphia – Career and Advanced Technology Center, New Facility
The Community College of Philadelphia’s new Career and Advanced Technology Center (CATC) is progressing in West Philadelphia. Mechanical, Electrical and Plumbing rough-ins continue at the interior wall and ceiling level and fire protection systems will follow.
Masonry work continues as well as exterior and interior metal framing. The building enclosure systems are expected to be completed by end of summer or early fall.
Recently, the on-grade concrete slabs were completed on the first floor. This project is scheduled for a February 2022 completion.
School District of Philadelphia – Paul L. Dunbar School, Restoration
Another School District of Philadelphia school project that is wrapping up is the restoration to the Paul L. Dunbar School. The outdated building exterior was in poor shape, with deteriorated masonry around the parapet of the building.
The restoration includes the installation of galvanized steel inlets to replace the rusted ungalvanized ones, the rebuilding of masonry, and the repointing of mortar joints. The project is a restoration of a beautiful WPA funded school. Substantial completion is expected by end of summer.
Springfield School District – Springfield High School, Existing High School Demolition and Visitor Side Bleacher Construction
In Springfield, PA, the new Springfield High School has just been completed. Demolition of the existing High School has begun and is on schedule for completion at the end of the summer.
The Visitor Side Bleacher building footing and foundations have recently been completed. Next up are the masonry walls and door frames as well as site work grading for the athletic fields and tennis courts.
Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC) and Parking Structure, New Facilities
The new PennDOT Regional Traffic Management Center in King of Prussia is progressing nicely, with the continued forming of concrete footings and foundation walls. SG serves as the design component of the Heim Construction Design-Build team for this project. At the accompanying parking garage, work has been completed.
It is always exciting to watch our design work become reality! We would like to thank our clients, consultants, contractors, and all other team members for your dedication and support of the on-going efforts for these projects!
Learn more about these and other exciting SCHRADERGROUP projects here!
SCHRADERGROUP Construction Progress – April 2021
SCHRADERGROUP’S projects are quickly becoming a reality as construction continued throughout April. The team has been hard at work with construction administration for a variety of projects. A few of our construction projects that are underway include: two projects for the School District of Philadelphia, the Community College of Philadelphia’s new Career and Advanced Technology Center, the new Upper Merion Area High School, and the new PennDOT District 6.0 Regional Traffic Management Center and Parking Structure.
School District of Philadelphia – Anne Frank Elementary School, Renovations
Construction continues at Anne Frank Elementary School in northeast Philadelphia. Interior and exterior metal studwork and HVAC ductwork continues while exterior brick work is 80% complete. In the existing building, new VCT flooring has been installed.
School District of Philadelphia – Paul L. Dunbar Promise Academy, Masonry Investigation
Moving into Templetown, masonry restoration work at the Paul L. Dunbar School has finally begun. The historic academy north of center city serves grades k-8 and the façade was in serious need of repair. Old brick parapets were removed and reconstructed with new reinforced and grouted CMU, the exterior brick wythe was reconstructed as well and new flashing and anchors were installed.
This project shows the importance of masonry investigations, as the existing steel angle lintels were severely deteriorated.
Community College of Philadelphia – Career and Advanced Technology Center, New Facility
In West Philadelphia, the new Career and Advanced Technology Center for the Community College of Philadelphia is coming along nicely. The steel frame is being erected from the ground floor level while footings and foundations are ongoing at the first-floor level.
Upper Merion Area School District – Upper Merion Area High School, New Facility
In King of Prussia, the new high school is taking shape. The structural steel and foundation/underground work is ongoing and concrete slabs are underway.
Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC) and Parking Structure, New Facility
In King of Prussia, the grading for the RTMC building pad is ongoing. Rebar is on site and concrete footings are being poured. The formwork erection for the southwest retaining wall is recently underway.
The parking structure is progressing quickly. The curtain wall framing at the stairs, the stair railing, electrical conduit, and plumbing piping have all been installed and concrete washes are complete. The roof membrane installation has been recently completed as well.
As the weather improves and work continues, it is exciting to watch these projects come to fruition. We would like to thank all of our clients, consultants, contractors, and supporters for your dedication and support!
Learn more about these and other exciting SCHRADERGROUP projects here!