SCHRADERGROUP Construction Progress – Summer 2021

As we move into the middle of summer, many of our construction projects are now really starting to take shape. A few of the construction projects underway include the new Upper Merion Area High School, additions and renovations to Anne Frank Elementary School for the School District of Philadelphia, the new Career and Advanced Technology Center for the Community College of Philadelphia, the masonry restoration of the Paul L. Dunbar School in Philadelphia, the demolition of the existing Springfield High School, and the PennDOT District 6.0 Regional Traffic Management Center, among others.

Upper Merion Area School District – Upper Merion Area High School, New Facility1-Upper-Merion_Area-High-School_SCHRADERGROUP_May-Construction-Progress

Construction on the new Upper Merion Area High School continues into the heat of the summer. Infrastructure is being installed and is on pace for a September 2022 completion, just in time for Upper Merion Area School District high school students to start their new school year. Upon completion of and move into the new facility, demolition of the existing facility will begin. Once that demolition is complete, new playing fields will be constructed in its place.

2-Upper-Merion_Area-High-School_SCHRADERGROUP_May-Construction-Progress

This month, large Glulam Beams continue to be erected in the common areas. In the theater wing, the steel is in place for the stage as the auditorium takes shape.

3-Upper-Merion_Area-High-School_SCHRADERGROUP_May-Construction-Progress

School District of Philadelphia – Anne Frank Elementary School, Additions and Renovations1-Anne-Frank-Elementary-School_SCHRADERGROUP_May-Construction-Progress

Work on the Anne Frank Elementary School continues in Northeast Philadelphia. Metal panels have been installed on 75% of the new construction areas while the glass and glazing installation is 50% complete.

2-Anne-Frank-Elementary-School_SCHRADERGROUP_May-Construction-Progress

Acoustic ceiling tile and vinyl composite tile installation continues while the walls are being painted. Ceramic tile flooring has started in the toilet rooms as well. A new feature this month are the railings being installed in the new stairways.

3-Anne-Frank-Elementary-School_SCHRADERGROUP_May-Construction-Progress

Community College of Philadelphia – Career and Advanced Technology Center, New Facility1-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

The Community College of Philadelphia’s new Career and Advanced Technology Center (CATC) is progressing in West Philadelphia. Mechanical, Electrical and Plumbing rough-ins continue at the interior wall and ceiling level and fire protection systems will follow.

2-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

Masonry work continues as well as exterior and interior metal framing. The building enclosure systems are expected to be completed by end of summer or early fall.

3-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

Recently, the on-grade concrete slabs were completed on the first floor. This project is scheduled for a February 2022 completion.

4-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

School District of Philadelphia – Paul L. Dunbar School, Restoration1-Paul-L-Dunbar-School-SDP_SCHRADERGROUP_May-Construction-Progress

Another School District of Philadelphia school project that is wrapping up is the restoration to the Paul L. Dunbar School. The outdated building exterior was in poor shape, with deteriorated masonry around the parapet of the building.

2-Paul-L-Dunbar-School-SDP_SCHRADERGROUP_May-Construction-Progress

The restoration includes the installation of galvanized steel inlets to replace the rusted ungalvanized ones, the rebuilding of masonry, and the repointing of mortar joints. The project is a restoration of a beautiful WPA funded school. Substantial completion is expected by end of summer.

 

Springfield School District – Springfield High School, Existing High School Demolition and Visitor Side Bleacher Construction1-Springfield-High-School-Demolition_SCHRADERGROUP_May-Construction-Progress

In Springfield, PA, the new Springfield High School has just been completed. Demolition of the existing High School has begun and is on schedule for completion at the end of the summer.

2-Springfield-High-School-Bleacher_SCHRADERGROUP_May-Construction-Progress

The Visitor Side Bleacher building footing and foundations have recently been completed. Next up are the masonry walls and door frames as well as site work grading for the athletic fields and tennis courts.

 

Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC) and Parking Structure, New Facilities1-PennDOT-District-6.0-Regional-Traffic-Management-Center-RTMC_SCHRADERGROUP_May-Construction-Progress

The new PennDOT Regional Traffic Management Center in King of Prussia is progressing nicely, with the continued forming of concrete footings and foundation walls. SG serves as the design component of the Heim Construction Design-Build team for this project. At the accompanying parking garage, work has been completed.

 

It is always exciting to watch our design work become reality! We would like to thank our clients, consultants, contractors, and all other team members for your dedication and support of the on-going efforts for these projects!

Learn more about these and other exciting SCHRADERGROUP projects here!

SCHRADERGROUP Construction Progress – May 2021

As summer quickly approaches, construction work continues to accelerate on SCHRADERGROUP (SG) projects! The team has been hard at work with construction administration for a variety of projects, with some rapidly approaching final completion. A few of our construction projects underway include a new Emergency Operations Center in North Carolina, additions and renovations to the School District of Philadelphia’s Anne Frank Elementary School, the Community College of Philadelphia’s new Career and Advanced Technology Center, the new Upper Merion Area High School, and the new PennDOT District 6.0 Regional Traffic Management Center and Parking Structure, among others. A brief description of a few projects follow.

Chatham County, North Carolina – Emergency Operations Center (EOC)

Chatham_SCHRADERGROUP_May-Construction-Progress
In North Carolina, the grading of the site for the new Emergency Operations Center continues. Fine grading is completed on the east side of the site while work continues on the west side. The temporary entrance to the site has been removed and graded and work with the North Carolina Department of Transportation to connect the main entrance to the roadway has begun. Finally, the Cell Tower Structure was recently installed and the screening topsoil is complete.

School District of Philadelphia – Anne Frank Elementary School

1-Anne-Frank_SCHRADERGROUP_May-Construction-Progress

In Philadelphia, the additions and renovations to Anne Frank Elementary School are quickly progressing. The exterior brick work is now complete and the installation of windows and ceramic tile begins. Inside, the painting is still in progress while the acoustic ceiling tile grid installation begins.

2-Anne-Frank_SCHRADERGROUP_May-Construction-Progress

Community College of Philadelphia – Career and Advanced Technology Center

1-CCP-CATC_SCHRADERGROUP_May-Construction-Progress

In West Philadelphia, the steel framing is complete at the new Career and Advanced Technology Center for the Community College of Philadelphia and the crane has been removed. MEP rough ins above grade have started in addition to the Concrete Masonry Unit walls. This project is scheduled for substantial completion by February 2022.

2-CCP-CATC_SCHRADERGROUP_May-Construction-Progress

Upper Merion Area School District – Upper Merion Area High School

1-Upper-Merion-Area-High-School_SCHRADERGROUP_May-Construction-Progress

In King of Prussia, foundation work continues in the performing arts and gym/pool area of the new high school. In the classroom wing, concrete slabs have been poured. Out front, the curbs and asphalt have been installed in the parking lot. The most exciting update this month is that the site contractor is preparing to connect the site’s existing stream to the renovated stream area, which will be located near an outdoor amphitheater and teaching area to provide the students with science-based learning activities directly related to their campus.

2-Upper-Merion-Area-High-School_SCHRADERGROUP_May-Construction-Progress

Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC) and Parking Structure

1-RTMC_SCHRADERGROUP_May-Construction-Progress

Another SG project in King of Prussia, the new RTMC facility’s foundation is progressing nicely. Heim Construction continues to advance the concrete footings and foundation walls. This week, waterproofing of the concrete footings began as well.

2-RTMC_SCHRADERGROUP_May-Construction-Progress

The new adjacent parking structure is swiftly approaching completion. Installation of metal panel and soffit systems at the Penthouse are underway. The glazing, batten installation, metal louvre, site sign foundation, parking striping, and asphalt paving are all complete. Additionally, electric charging stations have been installed.

3-RTMC_SCHRADERGROUP_May-Construction-Progress

As the weather improves and work continues, it is exciting to watch these projects come to fruition. We would like to thank all of our clients, consultants, contractors, and supporters for your dedication and support!

Learn more about these and other exciting SCHRADERGROUP projects here!

SCHRADERGROUP Construction Progress – April 2021

SCHRADERGROUP’S projects are quickly becoming a reality as construction continued throughout April. The team has been hard at work with construction administration for a variety of projects. A few of our construction projects that are underway include: two projects for the School District of Philadelphia, the Community College of Philadelphia’s new Career and Advanced Technology Center, the new Upper Merion Area High School, and the new PennDOT District 6.0 Regional Traffic Management Center and Parking Structure.

School District of Philadelphia – Anne Frank Elementary School, Renovations

1_SCHRADERGROUP_Anne-Frank-Elementary-School_School-District-of-Philadelphia

Construction continues at Anne Frank Elementary School in northeast Philadelphia. Interior and exterior metal studwork and HVAC ductwork continues while exterior brick work is 80% complete. In the existing building, new VCT flooring has been installed.

2_SCHRADERGROUP_Anne-Frank-Elementary-School_School-District-of-Philadelphia

School District of Philadelphia – Paul L. Dunbar Promise Academy, Masonry Investigation

1_SCHRADERGROUP_Paul-Dunbar-Academy_School-District-of-Philadelphia

Moving into Templetown, masonry restoration work at the Paul L. Dunbar School has finally begun. The historic academy north of center city serves grades k-8 and the façade was in serious need of repair. Old brick parapets were removed and reconstructed with new reinforced and grouted CMU, the exterior brick wythe was reconstructed as well and new flashing and anchors were installed.

This project shows the importance of masonry investigations, as the existing steel angle lintels were severely deteriorated.

2_SCHRADERGROUP_Paul-Dunbar-Academy_School-District-of-Philadelphia

Community College of Philadelphia – Career and Advanced Technology Center, New Facility

1_SCHRADERGROUP_Community-College-of-Philadelphia_Career-and-Advanced-Technology-Center

In West Philadelphia, the new Career and Advanced Technology Center for the Community College of Philadelphia is coming along nicely. The steel frame is being erected from the ground floor level while footings and foundations are ongoing at the first-floor level.

2_SCHRADERGROUP_Community-College-of-Philadelphia_Career-and-Advanced-Technology-Center

Upper Merion Area School District – Upper Merion Area High School, New Facility

1_SCHRADERGROUP_Upper-Merion-Area-School-District-New-High-School

In King of Prussia, the new high school is taking shape. The structural steel and foundation/underground work is ongoing and concrete slabs are underway.

2_SCHRADERGROUP_Upper-Merion-Area-School-District-New-High-School

Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC) and Parking Structure, New Facility

1_SCHRADERGROUP_PennDOT_Regional-Traffic-Management-Center_RTMC

In King of Prussia, the grading for the RTMC building pad is ongoing. Rebar is on site and concrete footings are being poured. The formwork erection for the southwest retaining wall is recently underway.

2_SCHRADERGROUP_PennDOT_Regional-Traffic-Management-Center_Parking-Garage

The parking structure is progressing quickly. The curtain wall framing at the stairs, the stair railing, electrical conduit, and plumbing piping have all been installed and concrete washes are complete. The roof membrane installation has been recently completed as well.

3_SCHRADERGROUP_PennDOT_Regional-Traffic-Management-Center_Parking-Garage

As the weather improves and work continues, it is exciting to watch these projects come to fruition. We would like to thank all of our clients, consultants, contractors, and supporters for your dedication and support!

Learn more about these and other exciting SCHRADERGROUP projects here!