SCHRADERGROUP Construction Progress – Summer 2021, Part 2

Now that summer has come to an end, a few SG projects are wrapping up while construction continues on many others. A few of the construction projects currently underway include the additions and renovations to Knapp Elementary School for the North Penn School District, the demolition of the existing Springfield High School and construction of new athletic facilities for the new high school, the new PennDOT District 6.0 Regional Traffic Management Center, the new Upper Merion Area High School, additions and renovations to two School District of Philadelphia Schools, Anne Frank Elementary School and Benjamin Franklin Middle School, the new Career and Advanced Technology Center for the Community College of Philadelphia, and additions and renovations to two Council Rock School District Schools, Hilcrest Elementary School and Sol Feinstone Elementary School, among others.

North Penn School District – Knapp Elementary School, Additions and Renovations

1-Knapp-Elementary_School-North-Penn_SCHRADERGROUP_Summer-Construction-Progress

In Lansdale, PA, a phased plan for additions and renovations to Knapp Elementary School is underway. This project has a complex phasing schedule in place so that classes can remain uninterrupted as the school year begins.

2-Knapp-Elementary_School-North-Penn_SCHRADERGROUP_Summer-Construction-Progress

The first phases of the project included classroom renovations, many of which are complete. The remaining classroom renovations are underway at various stages.

3-Knapp-Elementary_School-North-Penn_SCHRADERGROUP_Summer-Construction-Progress

The renovations to the core of the building, including the new entry, cafeteria, and LGI are ongoing. Steel and glulam beams are fully installed in all of these spaces. An important milestone, the completion of the main entrance, is fast approaching. This addition will act as the connector for the two parts of the school while the renovations to the core are underway. The students will be using the gymnasium as a temporary cafeteria this fall.

4-Knapp-Elementary_School-North-Penn_SCHRADERGROUP_Summer-Construction-Progress

Springfield School District – Springfield High School, Existing High School Demolition, Visitor Side Bleacher, and Athletic Fields

1-Springfield-High-School-Demo-Bleacher_SCHRADERGROUP_Summer-Construction-Progress

In Springfield, PA, demolition work is speeding up. The existing Springfield High School is substantially demolished, the stone retaining wall construction is ongoing, and lot paving has begun for parking. After the completion of the existing high school’s demolition, work will begin on new athletic fields, turf fields, and tennis courts where the original school stood.

2-Springfield-High-School-Demo-Bleacher_SCHRADERGROUP_Summer-Construction-Progress

The visitor side bleacher construction is progressing and is expected to be completed in time for the first home football game at the new high school and stadium.

3-Springfield-High-School-Demo-Bleacher_SCHRADERGROUP_Summer-Construction-Progress

Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC)

In King of Prussia, PA, concrete slab placement at the new Regional Traffic Management Center has been completed on each floor. Waterproofing of the concrete footings is complete, the underground plumbing has been installed, and the steel column baseplates are in place.

1-PennDOT-Regional-Traffic-Management-Center_SCHRADERGROUP_Summer-Construction-Progress

The site retaining wall is complete, as is the majority of steel and decking. CMU installation in ongoing and interior metal stud framing has begun.

2-PennDOT-Regional-Traffic-Management-Center_SCHRADERGROUP_Summer-Construction-Progress

Upper Merion Area School District – New Upper Merion Area High School

1-Upper-Merion-Area-High-School_SCHRADERGROUP_Summer-Construction-Progress

Moving on down the road in King of Prussia, construction of the new Upper Merion Area High School continues. Structural steel framing for the major spaces is ongoing while the exterior envelope starts to give the building its form. Masons have been busy with brick work and CMU walls.

4-Upper-Merion-Area-High-School_SCHRADERGROUP_Summer-Construction-Progress

As concrete slabs are completed throughout the facility, MEP rough-in work continues closely behind. Activity on site recently picked up as carpenters started on the interior partitions.

3-Upper-Merion-Area-High-School_SCHRADERGROUP_Summer-Construction-Progress

Now that the underground tunnel is  complete, the gym and pool areas are getting footings and foundations started.

5-Upper-Merion-Area-High-School_SCHRADERGROUP_Summer-Construction-Progress

School District of Philadelphia – Anne Frank Elementary School, Additions and Renovation

1-Anne-Frank-Elementary-School_School-District-of-Philadelphia_SCHRADERGROUP_Summer-Construction-Progress

In Philadelphia, construction has moved quickly at Anne Frank Elementary School, with the addition complete in time for the new school year.

2-Anne-Frank-Elementary-School_School-District-of-Philadelphia_SCHRADERGROUP_Summer-Construction-Progress

Community College of Philadelphia – New Career and Advanced Technology Center

1-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

Staying with construction projects in Philadelphia, the new Career and Advanced Technology Center (CATC) for the Community College of Philadelphia is progressing nicely. All building trades have been working diligently on both the exterior and interior of the building, with the next major milestone being the completion of the building enclosure in the next few weeks.

2-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

The new CATC will offer excellent views of the Philadelphia Skyline. The project is on track for a February 2022 completion.

3-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

Bristol Township School District – Benjamin Franklin Middle School, Additions and Renovations

1-Benjamin-Franklin-Middle-School_School-District-of-Philadelphia_SCHRADERGROUP_Summer-Construction-Progress

North of Philadelphia, demolition work at Benjamin Franklin Middle School is complete and interior framing and stud work has started.

3-Benjamin-Franklin-Middle-School_School-District-of-Philadelphia_SCHRADERGROUP_Summer-Construction-Progress

Additionally, site work for the new addition is in progress, with concrete footings now installed.

2-Benjamin-Franklin-Middle-School_School-District-of-Philadelphia_SCHRADERGROUP_Summer-Construction-Progress

Council Rock School District – Hillcrest Elementary Schools, Additions and Renovations

1-Council-Rock-School-District_Hillcrest-Elementary-School_SCHRADERGROUP_Summer-Construction-Progress

Heading north towards Council Rock School District, SG has wrapped up interior demolition at the Hillcrest Elementary School, with the kitchen, administration, toilets and library areas completely demolished. Rough in has started throughout for all trades.

2-Council-Rock-School-District_Hillcrest-Elementary-School_SCHRADERGROUP_Summer-Construction-Progress

During construction, Hillcrest Elementary School students will be temporarily moved to a vacant CRSD school for the upcoming school year. The project is moving ahead quickly with E&S controls and fencing already in place.

Council Rock School District – Sol Feinstone Elementary Schools, Additions and Renovations

3-Council-Rock-School-District_Sol-Feinstone-Elementary-School_SCHRADERGROUP_Summer-Construction-Progress

Staying in Council Rock School District, SG is working on phased renovations for another elementary school, Sol Feinstone Elementary School. Unlike Hillcrest, which will have students attending classes at a nearby vacant elementary school, Sol Feinstone will be 100% occupied throughout construction. This will result in the construction of temporary classrooms and a temporary egress stair that contains a pathway for students to safely traverse while the addition is underway.

1-Council-Rock-School-District_Sol-Feinstone-Elementary-School_SCHRADERGROUP_Summer-Construction-Progress

The summer phases for this project are currently under construction, and interior and exterior demolition has recently started. E&S controls are in place and excavation for the new addition is currently underway. Pier footings and foundations at the new classroom addition are ongoing as well.

2-Council-Rock-School-District_Sol-Feinstone-Elementary-School_SCHRADERGROUP_Summer-Construction-Progress

It is always exciting to watch our design work become reality! We would like to thank our clients, consultants, contractors, and all other team members for your dedication and support of the on-going efforts for these projects!

Learn more about these and other exciting SCHRADERGROUP projects here!

Springfield School District’s New Springfield High School is Complete!

The SCHRADERGROUP (SG) team, in association with our design partner Perkins&Will of Chicago, is happy to announce that Springfield School District’s new Springfield High School is now complete!

2-Learning-Stair_SCHRADERGROUP_Springfield_School_District_High_School_Perkins&WillPhoto courtesy of Todd Mason from Halkin | Mason Photography.

Constructed on the southeast corner of the existing high school’s campus, the goal of the new facility is to provide the school district with a complex that will serve the community for the next 50 years. Perkins&Will and SG provided programming, planning and design services for the new high school complex that encompasses 230,000 SF on a 25-acre campus. The school will immediately serve over 1,450 students.

3-Aerial-2_SCHRADERGROUP_Springfield_School_District_High_School_Perkins&WillPhoto courtesy of Todd Mason from Halkin | Mason Photography.

Consistent with the SG mission of creating next generation learning environments, the new high school employs an Academy Model that provides offerings in Art, Business, STE(A)M (Science, Technology, Engineering and Math), Humanities and Liberal Arts. The new facility includes an interior courtyard for outdoor learning as well as for gathering and common space. Unique to the facility is its inclusion of the District Administration within the structure of the facility.

4-Courtyard_SCHRADERGROUP_Springfield_School_District_High_School_Perkins&WillPhoto courtesy of Todd Mason from Halkin | Mason Photography.

Beyond the high school and District Administration, the project includes the design and construction of new site amenities, including the athletic fields, parking, and a stadium complex. Next up, SG will be engaged in the demolition of the existing high school, which will then lead to the construction of additional playing fields.

5-Athletics_SCHRADERGROUP_Springfield_School_District_High_School_Perkins&WillPhoto courtesy of Todd Mason from Halkin | Mason Photography.

The SG team is pleased to partner with Springfield School District on this wonderful project. To learn more about Springfield School District, click here.

6-Exterior-2_SCHRADERGROUP_Springfield_School_District_High_School_Perkins&WillPhoto courtesy of Todd Mason from Halkin | Mason Photography.

This project was completed in association with design architects Perkins&Will of Chicago, IL and the owner project representative CID Group of Berwick, PA. To learn more about Perkins&Will, click here.

7-Lobby_SCHRADERGROUP_Springfield_School_District_High_School_Perkins&WillPhoto courtesy of Todd Mason from Halkin | Mason Photography.

To learn more about the New Springfield High School project, and view more photos, please click here.

8-Auditorium_SCHRADERGROUP_Springfield_School_District_High_School_Perkins&WillPhoto courtesy of Todd Mason from Halkin | Mason Photography.

Thank you to Halkin | Mason Photography for the beautiful images captured of this great project. To learn more about Halkin | Mason Photography, please click here.

9-Corridor_SCHRADERGROUP_Springfield_School_District_High_School_Perkins&WillPhoto courtesy of Todd Mason from Halkin | Mason Photography.

SCHRADERGROUP Construction Progress – Summer 2021

As we move into the middle of summer, many of our construction projects are now really starting to take shape. A few of the construction projects underway include the new Upper Merion Area High School, additions and renovations to Anne Frank Elementary School for the School District of Philadelphia, the new Career and Advanced Technology Center for the Community College of Philadelphia, the masonry restoration of the Paul L. Dunbar School in Philadelphia, the demolition of the existing Springfield High School, and the PennDOT District 6.0 Regional Traffic Management Center, among others.

Upper Merion Area School District – Upper Merion Area High School, New Facility1-Upper-Merion_Area-High-School_SCHRADERGROUP_May-Construction-Progress

Construction on the new Upper Merion Area High School continues into the heat of the summer. Infrastructure is being installed and is on pace for a September 2022 completion, just in time for Upper Merion Area School District high school students to start their new school year. Upon completion of and move into the new facility, demolition of the existing facility will begin. Once that demolition is complete, new playing fields will be constructed in its place.

2-Upper-Merion_Area-High-School_SCHRADERGROUP_May-Construction-Progress

This month, large Glulam Beams continue to be erected in the common areas. In the theater wing, the steel is in place for the stage as the auditorium takes shape.

3-Upper-Merion_Area-High-School_SCHRADERGROUP_May-Construction-Progress

School District of Philadelphia – Anne Frank Elementary School, Additions and Renovations1-Anne-Frank-Elementary-School_SCHRADERGROUP_May-Construction-Progress

Work on the Anne Frank Elementary School continues in Northeast Philadelphia. Metal panels have been installed on 75% of the new construction areas while the glass and glazing installation is 50% complete.

2-Anne-Frank-Elementary-School_SCHRADERGROUP_May-Construction-Progress

Acoustic ceiling tile and vinyl composite tile installation continues while the walls are being painted. Ceramic tile flooring has started in the toilet rooms as well. A new feature this month are the railings being installed in the new stairways.

3-Anne-Frank-Elementary-School_SCHRADERGROUP_May-Construction-Progress

Community College of Philadelphia – Career and Advanced Technology Center, New Facility1-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

The Community College of Philadelphia’s new Career and Advanced Technology Center (CATC) is progressing in West Philadelphia. Mechanical, Electrical and Plumbing rough-ins continue at the interior wall and ceiling level and fire protection systems will follow.

2-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

Masonry work continues as well as exterior and interior metal framing. The building enclosure systems are expected to be completed by end of summer or early fall.

3-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

Recently, the on-grade concrete slabs were completed on the first floor. This project is scheduled for a February 2022 completion.

4-Community-College-of-Philadelphia_Career-Advanced-Technoloy-Center_SCHRADERGROUP_May-Construction-Progress

School District of Philadelphia – Paul L. Dunbar School, Restoration1-Paul-L-Dunbar-School-SDP_SCHRADERGROUP_May-Construction-Progress

Another School District of Philadelphia school project that is wrapping up is the restoration to the Paul L. Dunbar School. The outdated building exterior was in poor shape, with deteriorated masonry around the parapet of the building.

2-Paul-L-Dunbar-School-SDP_SCHRADERGROUP_May-Construction-Progress

The restoration includes the installation of galvanized steel inlets to replace the rusted ungalvanized ones, the rebuilding of masonry, and the repointing of mortar joints. The project is a restoration of a beautiful WPA funded school. Substantial completion is expected by end of summer.

 

Springfield School District – Springfield High School, Existing High School Demolition and Visitor Side Bleacher Construction1-Springfield-High-School-Demolition_SCHRADERGROUP_May-Construction-Progress

In Springfield, PA, the new Springfield High School has just been completed. Demolition of the existing High School has begun and is on schedule for completion at the end of the summer.

2-Springfield-High-School-Bleacher_SCHRADERGROUP_May-Construction-Progress

The Visitor Side Bleacher building footing and foundations have recently been completed. Next up are the masonry walls and door frames as well as site work grading for the athletic fields and tennis courts.

 

Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC) and Parking Structure, New Facilities1-PennDOT-District-6.0-Regional-Traffic-Management-Center-RTMC_SCHRADERGROUP_May-Construction-Progress

The new PennDOT Regional Traffic Management Center in King of Prussia is progressing nicely, with the continued forming of concrete footings and foundation walls. SG serves as the design component of the Heim Construction Design-Build team for this project. At the accompanying parking garage, work has been completed.

 

It is always exciting to watch our design work become reality! We would like to thank our clients, consultants, contractors, and all other team members for your dedication and support of the on-going efforts for these projects!

Learn more about these and other exciting SCHRADERGROUP projects here!

SCHRADERGROUP Construction Progress – March 2021

2021 has been off to quite a busy start here at SCHRADERGROUP! The team has been working diligently on multiple projects in both the K-12 and Public Safety markets, including Upper Merion Area High School, Chatham County (NC) Emergency Operations Center, Anne Frank Elementary School, Knapp Elementary School, the East Pennsboro Area School District’s Administration Office, and the PennDOT District 6.0 Regional Traffic Management Center and Parking Structure.

With the weather improving recently, construction progress has been speeding up! See below for details on each of these exciting projects.

Upper Merion Area School District – Upper Merion Area High School

UMASD-IMG_0225

This month, the site finally started to dry out. Structural steel is being erected and the site was buzzing with activity!

Chatham County, North Carolina – Emergency Operations Center (EOC)

Chatham Site Aerial

Early site work has been moving along on this North Carolina EOC project. The pond construction, on-site water, and rough grading over the culvert are all complete while off-site water and road grading remains ongoing.

The School District of Philadelphia – Anne Frank Elementary School

AnneFrank-1_IMG_9020

In Philadelphia, construction continues on the Anne Frank Elementary School. The concrete slabs are completed, and the CMU work is coming close behind. Both interior and exterior metal stud work is in progress.

AnneFrank-2_IMG_9009

North Penn School District – Knapp Elementary School

Knapp-Site

Phase 1 of Knapp Elementary School’s renovations and additions is nearly complete! An 8-classroom addition that includes a new bus entry canopy and vestibule will provide the swing space for the remainder of the renovation work. Demolition is set to start for the next phase, which will create a brand new Dining Commons, Large Group Instruction space, and secure entry.

East Pennsboro Area School District (EPASD) – District Administration Office

EPASD-1_IMG_9067

Up near Harrisburg, the District Administration Office for EPASD is coming along nicely. The exterior steel for the addition is complete and the concrete slab was poured last week. Interior stud work is currently in progress.

EPASD-2_IMG_9078

Department of General Services – PennDOT District 6.0 Regional Traffic Management Center (RTMC) and Parking Structure

RTMC-020

Back in Philly, the PennDOT RTMC building is off and running. The first section of retaining wall footing is being constructed and the grading for the building pad is underway.

RTMC-Parking_IMG_3474

The activity at the parking structure is bustling as well. Steel installation at the stair towers is complete and rebar has been installed at the stair landing in preparation for concrete pours. CMU wall installation is underway as well as stud framing, HM door installation, and the sealing of vertical joints.

 

We are so excited to see these designs finally coming to reality! Thank you to our wonderful consultants and partners, particularly Heim Construction, Bala Consulting Engineers and Alfred Benesch & Company in their great work with PennDOT.

Learn more about these and other exciting SCHRADERGROUP projects here!